Job TypeSurveying an Accident Scene
CountryIsrael
Project Date2014
CameraSamsung Smart Camera NX
Time Spent in the Field30 min
DatuSurvey savings2 hours in the field + immediate sc

The Project Task

The required task was to survey and draft a 3D CAD plan, with a measurement accuracy of better than 2 centimeters (5-6 hundredths of a foot), of an accident scene.

Surveying an Accident Scene Datumate Original Image

Original Effort Estimate

The original effort estimate for the surveying project, using conventional surveying techniques, was 4 hours. This appraisal was based on 2 hours in the field, using a Total Station device, and 2 hours in the office to draft the detailed CAD plan of the accident scene based on the Total Station measurements and the sketch done in the field. A key challenge was the need to complete the survey in a short time to minimize the impact on traffic in the vicinity of the accident area.

DatuSurvey™ Savings

Traffic Accident Scene Surveying - Vector Measurements - sub 2cm accuracy - Datumate

The actual time to survey the accident scene and prepare a 3D CAD model of the accident scene was only one hour. The time spent in the field was only 30 minutes: 15 minutes to photograph the accident scene, and an additional 15 minutes to measure several control points.

The accident scene was photographed with a regular Samsung Smart Camera NX 1000 camera (20-megapixel resolution) with a 16-mm wide-angle lens. A total of 45 images of the accident scene were made from the perimeter of the accident scene toward the center, with an image taken every 2 meters (6 feet).

To minimize foreground obstructions in the images, the camera was elevated above ground level by mounting it on an 8-meter (25-feet) telescopic pole, and was remotely controlled using the Samsung smartphone application via Wi-Fi. A total of 20 points were measured at the accident scene using a prism-less Total Station device; 10 of these points were used as
control points for the geo-referencing of the images. The selected control points were high-contrast, well-defined objects such as the center of cars wheels, etc.

It is important to point out that, by surveying the accident scene with a camera, it was possible to clear the area much faster than when surveying it using conventional methods. Moreover, surveying from the images allowed the extraction of additional measurements at later stages. The actual time spent in the office to geo-reference the images and draft the 3D
CAD plan of the accident scene directly on the images was two hours.

Results

A 3D CAD model of the accident scene in DXF format was generated by drafting directly on the oblique images using DatuSurvey™. In addition to the DXF file, a list of all measured points in PNT format was generated. This included the point names, codes, descriptions, coordinates, and their measurement accuracies in all axes. In total, 79 new measurements were made from the images. The measurement accuracy of all points was better than 2 centimeters (5-6 hundredths of a foot) in both position and elevation.

The survey in the field using a regular camera mounted on a telescopic pole proved to be rapid, effective, accurate and, furthermore, much safer, compared to surveying using conventional techniques. Overall, the surveyor saved significant time – 2 hours, which are so crucial during the car accidents. The accident scene was cleared faster and additional measurements were extracted from the images at a later stage.

Traffic Accident Scene Surveying - 3D CAD Model Datumate

See how your peers are using Datumate solutions...

A14 Road and Railway Intersection Surveying for SKANSKA

As part of the UK’s A14 improvement scheme which is one of the UK’s largest road projects, it was required to map a busy A14 highway junction including a highway intersection and a railway line. The complex mapping included multiple infrastructure layers (bridge, road and railway line) as well as an accurate snapshot of the surrounding buildings to avoid future damage claims during road reconstruction work.

Read this case study »

Quantity Check Surveying

Courts at Clarksburg is an area that is being prepared for building homes. The area surveyed is an open area where infrastructure work has been done. The objective of this project is to survey the area to check the level of filled slab areas in an effort to compare it to the planned levels. And also to check quantities of cut and fill needed to finish the prep work.

Read this case study »

Residential Community Surveying

The objective of this project is to survey a residential area and detect changes in structures for property taxation purposes. The area surveyed included about 50 houses which were clearly shown on an orthophoto and as a dense point cloud as well.

Read this case study »

Baseball Stadium Surveying

Doppler radar is being implemented in baseball and softball venues around the world to track the trajectory of pitched and hit balls. All physical obstructions that are within the azimuth of the Doppler radar field of view were identified using the model.

Read this case study »
Scroll to Top